This project features a 160,106 square foot pre-engineered metal warehouse with three mezzanines. The building includes unit masonry stem walls, metal siding, a metal roof system, and a concrete slab-on-grade foundation. Scope also includes comprehensive sitework improvements, construction of a new fuel facility, TxDOT roadway infrastructure, and development of surrounding outparcels.
Commencement of Site Construction Date: April 14, 2025
Commencement of Building Construction Date: June 23, 2025
Substantial Completion and Opening Date: October 31, 2025
Final Completion Date: November 30, 2025