Costco Liberty Hill

Project Overview

This project features a 160,106 square foot pre-engineered metal warehouse with three mezzanines. The building includes unit masonry stem walls, metal siding, a metal roof system, and a concrete slab-on-grade foundation. Scope also includes comprehensive sitework improvements, construction of a new fuel facility, TxDOT roadway infrastructure, and development of surrounding outparcels.

Commencement of Site Construction Date: April 14, 2025
Commencement of Building Construction Date: June 23, 2025
Substantial Completion and Opening Date: October 31, 2025
Final Completion Date: November 30, 2025

Project Details

Liberty Hill, Texas

Location

Current Projects

Project Type

Negotiated GMP

Delivery Method

160,106 SF

Project Size

The Team

Costco Wholesale Corporation

Owner/Client

Ware Malcomb

Architect

Winkelmann & Associates

Engineer

Nick Pennington

Project Manager